01Who needs a PCB screening
The requirement is aimed at a specific kind of project. All of the following have to be true.
- The whole building is coming down. The City of Palo Alto describes the scope this way:
This Program focuses on potential sources to urban runoff that may contain PCBs from whole building deconstruction.
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026) - The building dates from the years when PCBs were used in construction materials. The program covers
buildings constructed or remodeled between January 1, 1950 and December 31, 1980
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026) - The building is not a house and is not wood-framed. In Palo Alto’s wording:
Buildings that are either wood-framed, single-family residential, or two-family residential (duplex) are exempt and not considered applicable structures regardless of the age of the building.
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026)
In practice that means commercial, industrial, institutional and larger apartment buildings of concrete, masonry or steel, built or remodeled from 1950 through 1980. An ordinary single-family house does not need this screening, whatever its age. Each city writes its own exemptions, so check the applicant package of the city where the building stands.
Planning a demolition and not sure the rule applies? Give us the year built, the framing and the city.
Call 510-288-9993 02Where the rule applies, and where it does not
The screening comes from the regional stormwater permit issued by the San Francisco Bay Regional Water Quality Control Board. The Board describes the permit as covering municipal stormwater discharges from entities in Alameda, Contra Costa, San Mateo, Santa Clara, and Solano counties listed in the Order
(San Francisco Bay Regional Water Quality Control Board, Stormwater, checked 22 November 2026) It names the permit in force: The current permit, MRP 3, comprises Order Nos. R2-2022-0018 and R2-2023-0019.
(San Francisco Bay Regional Water Quality Control Board, Stormwater, checked 22 November 2026)
For our service area that means:
- San Mateo County, Santa Clara County and Alameda County cities: covered by the permit. Expect the PCBs screening form at the demolition permit counter.
- San Francisco: not among the counties the permit lists.
- Santa Cruz County: not among the counties the permit lists.
The County of Santa Clara states its own rule plainly: Starting July 1, 2019, all applicants proposing to demolish a building must complete a PCBs Screening Assessment Form.
(County of Santa Clara, Prevent PCB release during building demolitions, checked 22 November 2026) If your building is in San Francisco or Santa Cruz County, ask the local building department what it requires before demolition. We have not found a matching screening form there, and we will not sell you a screening that nobody asks for.
03Which materials are sampled
The screening looks at a short list of priority building materials. Santa Clara County describes them as certain building materials (e.g., caulks/sealants, thermal/fiberglass insulation, adhesive/mastic, rubber window seals/gaskets)
(County of Santa Clara, Prevent PCB release during building demolitions, checked 22 November 2026)
Samples are taken from each of those materials where it is present in the building, following the regional sampling protocol that the city packages refer to, the Protocol for Evaluating Priority PCBs-Containing Materials before Building Demolition. The laboratory reports the PCB concentration of each sample in parts per million.
04What happens at 50 parts per million
Fifty parts per million is the line that changes the project. Below it, the completed form goes in with the permit application. At or above it, the City of Palo Alto says the project must contact the appropriate state and federal agencies for notification and advanced approval
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026)
Santa Clara County adds a deadline for that notice: at least five working days in advance of the start of the demolition
(County of Santa Clara, Prevent PCB release during building demolitions, checked 22 November 2026)
This is why the screening should not be left until the week before the excavator arrives. Palo Alto warns applicants that required coordination with the Environmental Protection Agency and other agencies may take several months
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026)
05How the screening works with us
- Applicability. We go through the first part of the city’s applicant package with you: year built or remodeled, type of framing, type of building. Many projects end here, with a signed statement that the structure is not an applicable one.
- Site visit. For an applicable structure we find the priority materials, take the samples the protocol calls for, photograph and label each location and fill in a chain-of-custody form.
- Laboratory. The samples are analyzed for PCBs and the results come back as a concentration for each material.
- The form. We enter the results and our part of the consultant section. The applicant signs and files it with the demolition permit application. In Santa Clara County the filing is followed by a letter:
WPD staff will send a confirmation letter with an assigned PCB Identification Number (PCB ID#).
(County of Santa Clara, Prevent PCB release during building demolitions, checked 22 November 2026)
No government body certifies firms for this work. The City of Palo Alto notes: Currently there is no certification program for firms conducting PCBs surveys or abatement.
(City of Palo Alto, PCBs Deconstruction Program, checked 21 November 2026) We do not claim a certification that does not exist. What you get from us is careful sampling, a documented chain of custody and a correctly completed form.
07Timing and cost
Start when the demolition is first planned, not when the permit is filed. The site visit is short. The laboratory time and, if a result is high, the agency coordination are what take long.
The fee depends on the number of buildings and of materials to sample. We quote it on the phone once we know the building.